CAT · 2002 · Question 42 of 61

CAT 2002 QA Question 42 · Arithmetic - Time & Work

Answer it first: the answer and the solution appear right after.

Q42 Arithmetic - Time & Work MULTIPLE CHOICE

It takes 6 technicians a total of 10 hours to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 a.m. and one technician per hour is added beginning at 5 p.m., at what time will the server be complete?

→Arun, Varun and Tarun, if working alone, can complete a task in 24, 21, and 15 days, respectively. They charg…CAT 2025 QA Slot 1 →Ankita is twice as efficient as Bipin, while Bipin is twice as efficient as Chandan. All three of them start…CAT 2025 QA Slot 2 →Teams A, B, and C consist of five, eight, and ten members, respectively, such that every member within a team…CAT 2025 QA Slot 3 →Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days wo…CAT 2024 QA Slot 1