Explanation:

Let the amount of work done to build one wall = LCM (24, 32, 48) = 96 units.

Efficiency of A = 96/24 = 4 units/day
Efficiency of B = 96/32 = 3 units/day
Efficiency of C = 96/48 = 2 units/day

Total 12 walls are to be built. i.e., total work to be done = 12 × 96 = 1152 units

Now,

Work done by A in 1st 64 days = 4 × 64 = 256
Work done by B (next 24 days) = 3 × 24 = 72

Total work done by A and B = 256 + 72 = 328 units

Work remaining = 1152 – 328 = 824 units

So, Work done by C = 824 = 2 × no. of days C has to work

∴ No. of days C has to work = 824/2 = 412 days

Hence, option (a).