Explanation:

On 1st day 12 work was completed and on 2nd day 14 × 12 work i.e. 18th work

So, work remaining =1 - 12+18 = 38th

38th work is 60m2 

⇒ comlete work = 60 × 83 = 160 m2

Hence, option (a).