Roughly what percentage of the total work is carried out onsite?
Explanation:
Total man-hours spent on offshore work = 100 + 410 + 290 = 800
And total man-hours spent on onsite work = 90 + 100 + 150 = 340
∴ Percentage onsite work = 340/(800 + 340) ≈ 30%
Hence, option (c).