Explanation:

Let the total work to be done = LCM (60, 84) = 420 units.

Efficiency of Anil = 420/60 = 7 units/day
Efficiency of Bimal = 420/84 = 5 units/day

Work done by Anil in 10 + 14 days = 24 × 7 = 168 units

Work done by Bimal in 14 days = 14 × 5 = 70 units

∴ Work done by Charu = 420 – 70 - 168 = 182 units

Fraction of work done by Charu = 182/420 = 91/210

∴ Payment received by Charu = 91/210 × 21,000 = Rs. 9,100

Hence, option (a).